Managing Resource Management Plan Stages
Prerequisites
The following conditions must be met when you add or modify a resource management plan:
- The total CPU share of all resource pools does not exceed 99%.
- The total CPU limit of all resource pools does not exceed 100%.
Adding a Resource Management Plan Stage
- Log in to the GaussDB(DWS) console.
- Choose Clusters. Click the name of a cluster.
- Go to the Basic Information page and click the Resource Management tab in the navigation pane on the left.
- Go to the plan details page and click Add in the Plan stage area. On the Add Stage page, enter the stage name and configure the resource information. Confirm the configuration and click OK.
Modifying a Resource Management Plan Stage
- Log in to the GaussDB(DWS) console.
- Choose Clusters. Click the name of a cluster.
- Go to the Basic Information page and click the Resource Management tab in the navigation pane on the left.
- Switch to the Resource Management Plans tab page and click Modify in the Operation column of the plan stage.
- Modify parameters, such as the stage changing time and resource configurations.
Manually Changing the Resource Management Plan Stage
If a running plan needs to be switched to a stage in advance, you can manually do it.
- Log in to the GaussDB(DWS) console.
- Choose Clusters. Click the name of a cluster.
- Go to the Basic Information page and click the Resource Management tab in the navigation pane on the left.
- Switch to the Resource Management Plans tab page, click the switch button in the plan overview area, and select the target stage.
Importing/Exporting Resource Management Plan Stages
- Log in to the GaussDB(DWS) console.
- Choose Clusters. Click the name of a cluster.
- Go to the Basic Information page and click the Resource Management tab in the navigation pane on the left.
- Switch to the Resource Management Plans tab page. In the plan stages area, click Import/Export to import or export a resource management plan stage.
Deleting a Resource Management Plan Stage
- Log in to the GaussDB(DWS) console.
- Choose Clusters. Click the name of a cluster.
- Go to the Basic Information page and click the Resource Management tab in the navigation pane on the left.
- Switch to the Resource Management Plans tab page and click Deletein the Operation column of the plan stage.